Cayce, SC Launches $10 Million Drainage Improvement Project

Workers installing drainage pipes in Cayce, SC

Cayce, SC, September 23, 2025

News Summary

Cayce, South Carolina, has started a $10 million Avenues Drainage Improvement Project to combat ongoing flooding concerns, particularly near Knox Abbott Drive. Local residents express worry about property damage from flooding, with drainage systems playing a role in directing water into the creek. The project, which is about halfway completed, will install large 72-inch concrete pipes to improve stormwater management and aims for completion by summer 2026.

Cayce, SC Launches $10 Million Drainage Improvement Project Amid Ongoing Flooding Concerns

Flooding has become an ongoing challenge for residents of Cayce, South Carolina, particularly in areas near Knox Abbott Drive. To address these issues, the city has initiated a $10 million Avenues Drainage Improvement Project as rising water levels from rainstorms can quickly escalate from a few inches to several feet within a matter of hours.

Local residents have voiced their concerns over property damage caused by flooding, sharing their experiences in a community Facebook group. Many believe that drainage systems from 12th Street to 9th Street are a contributing factor to the problem, directing excess water straight into the creek. Several residents have witnessed significant flooding, with reports highlighting severe overflow in the area.

The Avenues Drainage Improvement Project aims to address these serious flooding concerns. Construction began over the summer and is currently estimated to be about halfway finished. The initiative focuses on installing large 72-inch concrete pipes that will greatly enhance stormwater management in the city.

A city spokesperson emphasized the administration’s dedication to tackling flooding challenges, while noting that runoff is not solely attributed to city management. The ambitious project is scheduled to continue through the summer of 2026, incorporating extensive modifications to the existing drainage system.

Residents have long dealt with the impacts of flooding, with one stating that this ongoing issue has persisted for years. The drainage project represents a significant step toward long-term resolution. A study conducted in 2015 had previously identified the necessity for major enhancements to Cayce’s stormwater drainage system, especially following the catastrophic flooding of that same year often referred to as a “thousand-year flood.”

The first phase of this improvement initiative involved constructing a retaining wall on Axtell Road, facilitating better water flow. City officials acknowledged that the drainage enhancements represent a large, long-term project rather than a quick repair. Plans for future work will also include laying down pipes under several roads, with repaving work set to follow.

The roads that will be impacted include Indigo Avenue, Honeysuckle Street, and Naples Drive. The city has secured a $10 million grant from the state to support the project, contributing to a total estimated cost of $23 million. Ongoing collaboration with state and federal partners is vital to obtain the remaining necessary funding.

As work continues on this crucial project, residents may encounter temporary road closures. To stay informed about updates regarding the project, including potential road closures and traffic changes, residents are encouraged to check the city’s project website and can sign up for text or email alerts. An information line is also available for residents who have questions about the project.

FAQs

What is the total cost of the Avenues Drainage Improvement Project?

The total estimated cost of the Avenues Drainage Improvement Project is $23 million.

When did construction on the project begin?

Construction crews have been working on the project since summer.

What type of pipes are being installed as part of the drainage project?

The project includes the installation of large 72-inch concrete pipes to improve stormwater management.

How long is the project expected to last?

The project is expected to continue through next summer and into 2026.

How can residents stay informed about the project?

Residents can stay informed about project updates, including road closures and traffic changes, via the city’s project website and can sign up for text or email alerts. An information line is available for residents who have questions about the project.

Key Features of the Drainage Improvement Project

Feature Details
Total Project Cost $23 million
Grant Funding $10 million from the state
Pipe Size 72-inch concrete pipes
Construction Start Date Summer 2023
Project Completion Date Expected Summer 2026
Roads Affected Indigo Avenue, Honeysuckle Street, Naples Drive

Deeper Dive: News & Info About This Topic

HERE Resources

Cayce City Manager Resigns Amid Leadership Struggles
Flash Flood Warning Initiated for Lexington and Saluda Counties
Traffic Disruptions on I-20 in Lexington County Due to Accidents
Columbia Approves $184 Million Budget Amid Financial Strain
Cayce to Begin Road Closures for Drainage Project
Cayce Appoints Michael Conley as New City Manager
Cayce City Council’s Funding for Chamber in Legal Limbo
Columbia Approves $18.2 Million Sewer System Upgrade
Cayce Avenues Drainage Project Set to Begin Improvements
Cayce City Council Faces Controversy Over Budget and Taxes

Additional Resources

STAFF HERE LEXINGTON WRITER
Author: STAFF HERE LEXINGTON WRITER

The LEXINGTON STAFF WRITER represents the experienced team at HERELexington.com, your go-to source for actionable local news and information in Lexington, Fayette County, and beyond. Specializing in "news you can use," we cover essential topics like product reviews for personal and business needs, local business directories, politics, real estate trends, neighborhood insights, and state news affecting the area—with deep expertise drawn from years of dedicated reporting and strong community input, including local press releases and business updates. We deliver top reporting on high-value events such as Woodland Art Fair, Crave Food and Music Festival, and Railbird Festival. Our coverage extends to key organizations like Commerce Lexington and Blue Grass Community Foundation, plus leading businesses in education, manufacturing, and technology that power the local economy such as University of Kentucky, Toyota Motor Manufacturing, and Lexmark. As part of the broader HERE network, including HEREBowlingGreen.com and HERELouisville.com, we provide comprehensive, credible insights into Kentucky's dynamic landscape.

ADD MORE INFORMATION OR CONTRIBUTE TO OUR ARTICLE CLICK HERE!
Advertising Opportunity:

Stay Connected

More Updates

Cloudy morning in Lexington SC with signs of sunshine

Lexington, SC Weather Update

Lexington, SC, December 3, 2025 News Summary This morning in Lexington, SC, residents experienced cloudy skies with a temperature of 43°F. As the day progresses, temperatures

Would You Like To Add Your Business?

Sign Up Now and get your local business listed!